• Home
  • News
  • Engineering
  • Knowledge Hub
  • Resources
No Result
View All Result
Newsletter
Construction Front | Industry Knowledge Hub, News Portal
  • Engineering
  • News
  • Knowledge Hub
  • Resources
  • Contact Us
  • About us
Construction Front | Industry Knowledge Hub, News Portal
  • Home
  • News
  • Engineering
  • Knowledge Hub
  • Resources
No Result
View All Result
Newsletter
Construction Front | Industry Knowledge Hub, News Portal
No Result
View All Result
Home Knowledge Hub Claims & Contract Administration
What are prolongation costs

Prolongation Costs and Claims in Construction Contracts

Denys S. by Denys S.
April,2026
in Claims & Contract Administration, Knowledge Hub
0 0
0
301
SHARES
2.7k
VIEWS
Share on EmailShare on TwitterShare on LinkedinShare on Facebook

Delays are, unfortunately, a common occurrence in construction projects and are often associated with significant cost impacts. When delays are caused by the client or principal and extend the project’s completion date, the contractor may be entitled to recover prolongation costs — the additional time-related expenses incurred due to remaining on site longer than originally planned.

These costs are distinct from disruption claims or liquidated damages, and typically arise when an Extension of Time (EOT) is granted. Yet, despite being frequently referenced in negotiations and disputes, prolongation costs are often misunderstood — both in terms of what they cover and how they should be assessed.

This article explores the concept in detail, including how prolongation claims arise, how they differ from other delay-related entitlements, and provides a brief overview of how they can be quantified.

What are prolongation costs?

Prolongation costs refer to the additional expenses a contractor incurs when a construction project takes longer to complete than originally planned, due to delays caused by the client (or principal) or circumstances beyond the contractor’s control. 

These delays may result from unforeseen latent conditions (such as hidden defects, utilities issues, or soil contamination) or external factors like supply chain disruptions caused by events such as the COVID-19 pandemic. Under the terms of most modern construction contracts, the contractor is typically entitled to recover these time-related costs for remaining on site longer than initially anticipated.

What are prolongation costs

Typical examples of prolongation costs include, but are not limited to:

Prolongation Costs

Examples

Site Overheads

Site management salaries, plant hire, utilities, insurance, accommodation costs

Head Office Overheads

Administrative salaries, office-related costs

Financing Costs

Interest on loans or financial charges incurred due to delays

Example of Prolongation in Construction Projects

A common example of prolongation costs occurs when contractors encounter latent conditions on site, such as buried utilities, archaeological artifacts, or contamination, discovered during excavation. These issues can take weeks, months, or even years to resolve, causing significant program delays and financial strain on the contractor, who could not have predicted or priced these risks during the bidding phase.

Real World Examples:

  1. Sydney Light Rail Project (Australia) – During the construction of Sydney’s Light Rail network, contractors encountered contaminated soil and unmapped utilities. The discovery of contaminated ground required extensive testing and remediation, causing several months of delays. The project’s timeline was also affected by the need to divert utilities that were not originally documented. These unforeseen issues led to prolongation costs as contractors had to extend their time on-site to manage the delays, requiring additional resources and time. (More on Sydney’s troubled $2.1bn light rail project delayed again)
  2. Boston’s Big Dig (USA) – During the construction of Boston’s Central Artery/Tunnel Project (commonly known as the “Big Dig”), contractors faced numerous delays due to buried utilities and contaminated soil. The discovery of underground oil tanks and hazardous materials led to prolonged excavation work and forced the project to extend beyond its original completion date. These issues added significant costs to the project, which were primarily driven by the extended timelines and the need to address the unforeseen contamination. (More on: The Big Dig: Learning from a Mega Project)
  3. Crossrail Project (London, UK) – During the construction of Crossrail, London’s underground rail network, contractors encountered buried utilities and contaminated ground. The discovery of hazardous materials and uncharted infrastructure led to significant delays and extended the timeline. These unforeseen conditions caused prolongation costs as additional time and resources were required for remediation and to reroute utilities. More on: Crossrail delay: The report | London City Hall

What is a Prolongation Claim?

A prolongation claim is a formal request submitted by a contractor to recover the additional costs of staying on site longer than originally planned, following a delay that was not their fault. These claims typically arise when an Extension of Time (EOT) is granted for delays caused by the client, principal, or events beyond the contractor’s control.

It is important to note that while an EOT gives relief from liquidated damages, it doesn’t automatically entitle the contractor to cost recovery. To claim prolongation costs, the contractor must go a step further — they must prove that the delay impacted the critical path of the program and that the additional costs were a direct result of that delay.

Prolongation claims differ from disruption or acceleration claims in that they focus solely on time-related costs. These may include extended site overheads, head office allocations, and financing costs — all of which must be supported by proper documentation. Typically, the strength of a prolongation claim depends on well-maintained cost records, program updates, and evidence showing that reasonable steps were taken to mitigate the delay’s impact.

How to Calculate Prolongation Costs?

Calculating prolongation costs involves demonstrating the financial impact of a delay on the contractor’s operations. The process begins with establishing that the delay affected the project’s critical path — meaning it directly contributed to an extension of the overall completion date. Once this link is proven, the following cost categories are typically considered:

 Site Overheads: These include project-specific expenses that continue throughout the delay period, such as site management salaries, temporary facilities, utilities, security, and plant or equipment hire.

  • Head Office Overheads: Indirect costs from the contractor’s corporate operations, which are often apportioned to the delayed project using formulas such as the Emden or Hudson method.

  • Financing Costs: Interest on loans or extended working capital needed to support ongoing operations during the delay.

  • Other Direct Costs: These may include additional insurance premiums, accommodation, demurrage, or extended warranties tied to the delayed duration.

The most common methods used to quantify these costs are:

  • Actual Cost Method: Based on verifiable expenses during the extended period, supported by project accounting records.

  • Formula-Based Methods: Such as the Hudson, Emden, or Eichleay formulae, generally used for head office overhead recovery.

  • Preliminaries Rate Method: Applying daily or weekly rates from the contract preliminaries for ongoing site costs (typically, explicitly detailed under the construction agreement).

Regardless of the method used, the contractor must ensure the figures are evidence-based, consistent with the contract, and reflective of the true additional burden of staying on site longer.

The Hudson Formula

The Hudson Formula is a widely used method for calculating prolongation costs due to project delays. It helps quantify time-related costs, such as site overheads, plant hire, insurance, and accommodation, when delays extend the project timeline.

The formula is as follows:

Prolongation Cost= (Total Project Overheads / Original Duration) × Delay Period

Where:

  • Total Site/Project Overheads refers to all costs incurred on-site (e.g., management, machinery, utilities).

  • Original Duration is the initially agreed project timeline.

  • Delay Period is the period the contractor remains on site due to delays.

This formula allows contractors to claim a fair portion of the overheads based on the extended project duration, provided they can substantiate the delay was outside their control. Proper documentation, such as updated project timelines and cost records, is essential to support the claim.

Submitting a Prolongation Claim

Once prolongation costs have been calculated, pursuing a successful claim involves demonstrating entitlement, causation, and quantum — typically through structured documentation and contract-compliant processes. Key steps include:

  1. Notify the Delay Promptly: Follow the contract’s notice provisions, such as early warning notices or notice of delays, to inform the principal of the delay event as soon as it occurs.

  2. Secure an Extension of Time (EOT): Ensure the delay has been formally acknowledged and an EOT has been granted. Without this, there is no basis for claiming prolongation costs.

  3. Prepare the Claim in Full: Structure the variation claim clearly, typically following the SCL (Society of Construction Law) Protocol framework:

    • Cause: Describe the event and how it arose.

    • Effect: Demonstrate the impact on the critical path and project completion.

    • Entitlement: Refer to the relevant contractual clause.

    • Substantiation: Provide detailed evidence to support the cost claim.

  4. Support with Contemporaneous Records: Include updated programs, site diaries, cost reports, resource logs, and correspondence that demonstrate both the delay and the associated expenses.

  5. Show Mitigation Measures: Detail any reasonable steps taken to reduce or avoid the delay’s impact — a critical factor in the principal’s assessment of the claim.

A well-prepared prolongation claim is not just a matter of entitlement — it is about telling a clear, credible story backed by records, aligned with the contract, and grounded in accurate cost data.

FAQ - Prolongation Costs and Claims

Prolongation vs EOT vs Disruption Costs / Claims

To better understand how prolongation cost and claims fit within the broader context of construction delay entitlements, it helps to distinguish them from disruption and Extension of Time (EOT) claim:

Category

Extension of Time (EOT)

Disruption

Prolongation

Definition

Additional time granted to complete the project due to delays beyond the contractor’s control

Loss of productivity or efficiency in executing the works

Additional costs incurred from remaining on site longer due to delays

Entitlement

Provides relief from liquidated damages, but not automatically from cost recovery

Entitles the contractor to recover costs arising from inefficiencies

Entitles the contractor to recover time-related costs associated with extended site presence

Cause

Delays caused by the principal or external events

Disruption in planned sequence of work or inefficient working due to interference or late access

Delays caused by events beyond the contractor’s control, often following an EOT

Focus

Time

Productivity

Cost

Acceleration Claim vs Prolongation Claim

An acceleration claim arises when a contractor is required to speed up the work to recover lost time due to delays. This typically involves additional costs, such as overtime or extra resources, to meet the original deadline.

A prolongation claim, on the other hand, seeks compensation for the additional time-related costs incurred when the project is delayed beyond the original schedule, typically due to factors outside the contractor’s control. This covers extended overheads, financing costs, and other time-based expenses.

In short, acceleration claims are for speeding up the project, while prolongation claims are for the costs of extended project duration.

Need Help with Prolongation Costs and Claims?

Do not hesitate to contact us (click here) for specialised advice in the construction industry. 

Sources

  • DELAY AND DISRUPTION PROTOCOL by the Society of Construction Law (SoCLA) – 2nd_Edition_Final
  • The Big Dig: Learning from a Mega Project | APPEL Knowledge Services
  • Crossrail delay: The report | London City Hall
  • The two Hudson Formulas
  • Assessing Loss and Expenses Claim by Prolongation Cost
  • The Hudson Formula SCL Paper 230.pdf

Disclaimer: The articles on this blog are for informational and educational purposes only and do not constitute legal advice. While we strive to provide accurate and up-to-date information on construction law, regulations may vary by jurisdiction, and legal interpretations can change over time.

Tags: claimsClaims & Contract Administrationconstruction lawcontract managementdelay analysisprolongation
Previous Post

ACCIONA and Eiffage to Deliver Madrid’s New Formula 1 Urban Circuit

Next Post

ACCIONA acquires Machu Picchu Transmission Line Concession in South Peru

Denys S.

Denys S.

Denys Schwartz is a civil engineer and certified professional (PMP, CP3P, CAIA) with more than 15 years of experience in the construction industry, specialising in construction contracts, procurement, claims, delay analysis, and contract management for major infrastructure and energy projects. He holds a postgraduate degree in Corporate Finance and has worked on multibillion-dollar projects across Australia, Brazil, and other international markets — including the Sydney Metro and major renewable energy programs — supporting projects from development, transactions, and procurement through to delivery, claims, and dispute resolution

Related Posts

pre_construction_services_contract_infographic_900x600pre_construction_services_contract_infographic_900x600
Knowledge Hub

How a Pre-Construction Services Contract (PCSA) Works (And When to Use It)?

by Denys S.
April,2026
Construction infographic showing how two-stage tendering works, with Stage 1 contractor selection, PCSA execution, Stage 2 preconstruction development, and the final construction contract.
Knowledge Hub

How Two Stage Tendering Works? (And When to Use it)

by Denys S.
April,2026
Construction infographic comparing GMP and lump sum contracts, showing GMP as a later price ceiling with higher transparency and evolving scope, versus lump sum as an earlier fixed price with mature scope and early risk transfer
Knowledge Hub

GMP vs Lump Sum in Construction: What’s the Difference?

by Denys S.
April,2026
Editorial infographic explaining what a Guaranteed Maximum Price means in construction, showing a GMP cost cap above direct costs, contractor fee, contingency, and owner cost certainty.
Knowledge Hub

What Is a Guaranteed Maximum Price (GMP) in Construction? (And How It Works?)

by Denys S.
April,2026
nfographic showing the two-phase structure of progressive design-build, with early collaborative development in Phase 1 and construction execution in Phase 2
Knowledge Hub

What Is Progressive Design-Build? How It Works and When to Use It

by Denys S.
April,2026
Next Post
ACCIONA acquires Machu Picchu Transmission Line Concession in South Peru

ACCIONA acquires Machu Picchu Transmission Line Concession in South Peru

CVC DIF’s Ottoway Expands UK Presence with Acquisition of Two Student Accommodation Assets

CVC DIF's Ottoway Expands UK Presence with Acquisition of Two Student Accommodation Assets

SLB-Sener-ACCIONA JV Awarded FEED Contract for AEB Amsterdam’s Aurora Carbon Capture Project

SLB-Sener-ACCIONA JV Awarded FEED Contract for AEB Amsterdam’s Aurora Carbon Capture Project

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

I agree to the Terms & Conditions and Privacy Policy.

Stay Connected

Join our newsletter!

Newsletter

Newsletter

Stay at the front of the construction industry with the latest news, market trends, and project insights — delivered by ConstructionFront.com

Name
Enter your email address
LinkedIn Twitter Youtube Instagram Facebook Flirk

All about the construction world: the latest industry news and trends, practical knowledge, and unique tips to help you on your projects.

Site Map

  • Home
  • News
  • Engineering
  • Knowledge Hub
  • Resources
  • Contact Us
  • About us

Recent Posts

Red Oak Campus - Data Centre Map

DataBank secures $2 billion financing for Red Oak data centres in Dallas

April,2026
pre_construction_services_contract_infographic_900x600pre_construction_services_contract_infographic_900x600

How a Pre-Construction Services Contract (PCSA) Works (And When to Use It)?

April,2026

Copyright © 2023 ConstructionFront.Com | Affiliate Disclosure | Privacy Policy | Terms & Conditions

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
No Result
View All Result
  • Home
  • News
  • Engineering
  • Knowledge Hub
  • Resources

Copyright © 2023 ConstructionFront.Com | Affiliate Disclosure | Privacy Policy | Terms & Conditions

This website uses cookies. By continuing to use this website you are giving consent to cookies being used. Visit our Privacy and Cookie Policy.

ConstructionFront.com - Newsletter!

Stay at the front of the construction industry with the latest news, market trends, and project insights — delivered by ConstructionFront.com

Name
Enter your email address

Thanks, I’m not interested

Privacy Policy - Terms and Conditions